US Data Center Power Demand: 2030 Forecasts and Project Delays

Full research prompt

What are current US data center electricity forecasts for 2030 in TWh from EPRI, LBNL, Goldman Sachs and BCG, and how have post-midterm moratoriums and the roughly $1tn 2027 hyperscaler capex consensus changed the data center delay and cancellation rate in GW?

From Powering the AI Boom: Where the Grid Breaks First (2026-2030)

Jon Sinclair using Luminix AI
Jon Sinclair using Luminix AI Strategic Research
Key Takeaway from Powering the AI Boom: Where the Grid Breaks First (2026-2...

AI data centers will drive US electricity demand to 550-650 TWh by 2030, equivalent to 10-12% of total consumption, with forecasts varying widely from IEA's 425 TWh to BCG's 970 TWh due to differing assumptions on efficiency and growth. Grid constraints in key regions emerge as the first breaking point, risking supply shortages amid this surge.

EPRI’s February 2026 “Powering Intelligence 2026” scenarios project US data center electricity use (including crypto mining) of roughly 380–790 TWh by 2030, with explicit Low/Medium/High cases at 384/596/~794 TWh.[1][2][3]

These bottom-up scenarios draw on state-level project pipelines (under construction, advanced planning, early planning) and apply different execution rates: Low assumes most under-construction projects plus one-quarter of advanced-planning ones reach operation; High assumes all under-construction/advanced plus 30% of early-planning ones overcome constraints. The range is ~60% higher than EPRI’s 2024 estimates, reflecting accelerated announcements in the prior 18 months. Peak load is projected at 45–95 GW.[4]

LBNL’s June 2026 “United States Data Center Energy Usage Report: 2025 Update” (bottom-up, shipment- and equipment-based) gives a 2030 Reference Case of 649 TWh (~11.8% of projected US electricity), with a sensitivity range of 521–843 TWh (9.5–15.3%).[5][6]

This updates the prior report’s 2028 horizon. The Reference Case incorporates current IT equipment shipment forecasts, per-device power models, cooling simulations, and facility data. Sensitivity cases adjust parameters such as AI chip shipments/utilization, lifetimes, and idle power; compounded uncertainty bounds produce the 521–843 TWh envelope. AI servers are expected to drive the majority of growth.[7]

Goldman Sachs forecasts emphasize capacity and near-term power demand rather than a single 2030 TWh figure. Recent updates project US data center power demand rising from 31 GW (2025) to 66 GW (2027) and capacity reaching ~95 GW by 2030 (with later revisions to global/US capacity higher, e.g., US ~152 GW in one November 2026 note).[8][9][10] Annual TWh equivalents are not centrally featured in the retrieved 2026 materials (one secondary synthesis places GS/McKinsey around 300–400 TWh), as the firm focuses on GW-scale interconnection, utilization (~70%), and peak-share implications (e.g., 8.5% of summer peak by 2027).[11]

BCG’s 2024 analysis (widely cited in 2026 EPRI and secondary materials) projects the highest end of the spectrum, exceeding 1,000 TWh (or ~970–1,050 TWh range in some references) by 2030, implying ~80 GW firm-power shortfall.[12][12][13][14] This reflects aggressive assumptions on AI-driven computational demand growth and power intensity, positioning data centers as the dominant source of US load growth through the decade.

These forecasts diverge due to differing methodologies (project pipelines vs. equipment shipments vs. demand modeling) and assumptions on execution rates, efficiency gains, AI mix, and grid/power constraints. Ranges (e.g., EPRI 380–790 TWh; LBNL 521–843 TWh) underscore uncertainty; planners treat them as scenarios rather than point targets. LBNL and EPRI ranges overlap substantially in the mid-to-high hundreds of TWh, while BCG sits at the upper extreme.[8]

Post-2026 midterm elections (November 3, 2026), Democratic gains and new governors in key states (Texas, Georgia, Ohio, others) have intensified regulatory friction for data centers, with ~40–53% of the hyperscale pipeline in “newly flipped” or pause-leaning states and dozens of local ballot measures passing restrictions or bans.[15][16][17] A national moratorium remains low-probability, but subnational pauses, tighter permitting, community-benefit requirements, and tax-incentive scrutiny are rising. Hyperscaler capex consensus for 2027 centers around ~$1–1.2 trillion (Goldman Sachs: $1.2T for the largest five US hyperscalers, above ~$1.1T consensus; other estimates $1–1.3T), signaling sustained investment intent despite headwinds.[18][19]

This environment has modestly elevated delay/cancellation risk in GW terms, though pre-midterm analyses showed limited quantitative impact (~2.3 GW delayed by existing moratoriums out of ~38 GW projected for 2027 delivery, or ~6%).[20][21] Post-midterm, analysts flag higher friction concentrated in Texas (~38 GW tracked in one dataset), Georgia, Ohio, etc., with potential for multi-quarter or 1+ year slips on unpermitted/early-stage projects; cancellations of large projects rose notably in 2026 overall (43 cases totaling 11.2 GW cited in one tracker, with local opposition a leading reason).[17] The strong capex consensus supports continued buildout momentum (many hyperscaler projects already permitted or under construction), but shifts risk toward higher costs, on-site generation/back-up solutions, or selective project pruning where power access or community approval is uncertain. Actual realized delays/cancellations will depend on how long state-level pauses last and how utilities/regulators allocate interconnection queues.[22]

For competitors or entrants: Secure power early (or pursue behind-the-meter/on-site options); prioritize permitted sites in less contentious jurisdictions; model multiple demand scenarios (380–1,000+ TWh band); and factor rising regulatory/ community costs into economics, as the ~$1T+ 2027 capex signals hyperscalers will pay for priority but not absorb unlimited friction.