PJM 2028/2029 Auction Results and FERC Backstop Rulings
Full research prompt
What did FERC decide on PJM's 14.9 GW backstop procurement after June 2026, and what did the 2028/2029 PJM Base Residual Auction clear at in $/MW-day and MW short of target?
From Powering the AI Boom: Where the Grid Breaks First (2026-2030)
AI data centers will drive US electricity demand to 550-650 TWh by 2030, equivalent to 10-12% of total consumption, with forecasts varying widely from IEA's 425 TWh to BCG's 970 TWh due to differing assumptions on efficiency and growth. Grid constraints in key regions emerge as the first breaking point, risking supply shortages amid this surge.
FERC conditionally approved but suspended PJM’s Reliability Backstop Procurement (RBP, targeting the ~6.8 GW shortfall from the 2028/2029 BRA, not a standalone 14.9 GW figure) on September 29, 2026, and provided further guidance on cost allocation in a November 19, 2026 order, without launching the auction.[1][2]
PJM filed the one-time RBP proposal on July 31, 2026 (supplemented August 14), to procure new capacity addressing the shortfall primarily driven by large-load growth such as data centers. FERC accepted core elements (including a MW-weighted average offer cap of $555/MW-day) but suspended the tariff changes for five months (effective February 28, 2027, subject to refund) due to concerns over cost allocation, transmission owner exit rules, and load-serving entity (LSE) collateral requirements. It opened a hearing process or encouraged a swift Section 205 refile with fixes. PJM postponed the original September 30–October 21, 2026 bid window and refiled a revised proposal on October 29, 2026, incorporating updated large-load forecasts for better cost causation, revised collateral rules, and other adjustments.[3][4]
On November 19, 2026, FERC issued orders in docket ER26-3380-000 with concurrences from Commissioners See and Rosner. These acknowledged the urgent reliability need but emphasized that costs must be allocated to zones/customers driving the load growth (consistent with cost-causation principles) rather than spread broadly. The Commission provided a path forward for PJM to revise and refile promptly so procurement can proceed, while noting states’ roles in retail tariffs and curtailment rules. As of the latest reports, the auction has not occurred, and timelines point to a potential March 2027 or later start.[2][5]
- The initial target was the 6,831 MW UCAP shortfall (sometimes referenced in context of broader capacity needs around 14–15 GW in related planning), reducible by bilateral contracts/self-supply between large loads and new generation.[6]
- FERC accepted the $555/MW-day weighted-average cap and supplier collateral provisions but rejected or questioned cost allocation and opt-out elements in the original filing.
- PJM’s October 29 refile aimed to address these with more current data-center forecasts (hired CRA for independent analysis) and reduced utility risks; analysts noted the final procurement could shrink significantly (e.g., to hundreds of MW) depending on updated forecasts and bilaterals.[3]
This means market participants face ongoing uncertainty on timing and cost allocation for any backstop capacity; developers should monitor PJM’s next filing and stakeholder processes closely, while large-load customers (data centers) may face targeted cost responsibility or bilateral requirements.
The 2028/2029 PJM Base Residual Auction (BRA), held June 30–July 7, 2026, cleared at the FERC-approved price cap of $325/MW-day UCAP across the entire RTO footprint (down 2.5% from the prior auction’s $333.44 cap) and procured 138,318 MW UCAP, falling 6,831 MW short of the reliability requirement.[6][7]
PJM announced results on July 14, 2026. Every modeled Locational Deliverability Area (LDA) cleared at the uniform $325/MW-day cap under the temporary price collar (in place through 2029/2030). Cleared RPM capacity rose by 3,733 MW UCAP year-over-year, but this was insufficient to close the gap amid rising load forecasts (+1,375 MW peak load, largely from large loads/data centers). Total procured capacity (including Fixed Resource Requirement commitments of ~10,864 MW) reached ~149,182 MW UCAP, yielding a 14.7% total reserve margin versus the 20% target (14.4% installed reserve margin). The shortfall directly triggered the RBP proposal.[8]
- New generation and uprates cleared only ~525 MW UCAP; resources were dominated by existing gas, nuclear, and coal.
- PJM’s uncapped simulation showed a potential RTO-wide clearing price of ~$554.72/MW-day (ComEd LDA at $776.69/MW-day), highlighting the collar’s suppressive effect (estimated $13+ billion reduction in cleared value).[7]
- This was the third consecutive BRA clearing at the cap and the second with a material shortfall (prior year: ~6,516 MW short).
For competitors or new entrants, the capped but still-elevated price ($325/MW-day ≈ $118,625/MW-year) signals persistent scarcity value, while the shortfall and backstop create opportunities for new supply (with 2032 commercial operation deadlines in the RBP context) but also highlight risks from load-forecast volatility and allocation fights.[9]
PJM’s RBP is explicitly a transitional, one-time mechanism to bridge until broader market reforms and state actions restore fundamentals, with emphasis on better load forecasting and assigning costs to growth-driving customers.[10]
Commissioners stressed returning to market-based hedging and procurement rather than repeated backstops, alongside state-level retail tariffs, collateral, and curtailment priorities (e.g., protecting critical loads over data centers). PJM continues bilateral matchmaking between large loads and new generation in parallel.
This implies that long-term solutions will blend RTO procurement, state policy, and customer self-supply; new entrants should prioritize zones with documented load growth for cost allocation advantages and prepare for stricter interconnection and collateral rules.[5]
Key sources for these post-April 30, 2026 developments include official FERC orders and concurrences (November 2026), PJM’s July 14, 2026 BRA results release, and contemporaneous reporting from Utility Dive and RTO Insider. All quantitative figures (prices, MW shortfalls, dates) trace directly to these.
Sources
- {uri: "https://www.utilitydive.com/news/pjm-delays-backstop-procurement-ferc-data-center/831751/", title: "1"}
- {uri: "https://ferc.gov/news-events/news/commissioner-sees-concurrence-pjms-reliability-backstop-procurement-er26-3380-000", title: "2"}
- {uri: "https://www.utilitydive.com/news/pjm-revised-data-center-backstop-procurement-ferc/873551/", title: "3"}
- {uri: "https://datacenterfeed.com/article/pjm-reliability-backstop-procurement-ferc-suspension-doe-large-load-filing-october-2026", title: "4"}
- {uri: "https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-pjms-reliability-backstop-procurement-er26-3380", title: "5"}
- {uri: "https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2026-releases/20260714-pjm-capacity-auction-procures-138318-mw-of-generation-resources.pdf", title: "6"}
- {uri: "https://www.globenewswire.com/Tracker?data=nBEw6_9LN6Sf20hvcRFPauD5xctRV1fIuzGQNg2FL46PZ7Ag-wLUDWeezXlIVyJLZAjvWURYj0OFQUq7-PL4hqGkyRGnFHibLglZ9sllFKkjmD2xLj1klBFqTuIgfJRwSskKeXqaPnXGiYYRFwnBVrNZjA8xJ47gQsy-Hf_GU7pfSRO3JdDGKfKq7okoIO7X7y1jK3fGeqVj3VfGAQYcy8XeBypahqAeXTAwk2-sRSA_lmdmD_fbk2oR-tu9RnHXAFNTiLYFPPSfwR5YTo2pKrkumu2ol85Oal-Dkb6eNYY=", title: "7"}
- {uri: "https://kilowattlogic.com/news/pjm-2028-2029-capacity-auction-july-2026-watch", title: "8"}
- {uri: "https://www.enelnorthamerica.com/insights/blogs/pjm-2028-2029-capacity-auction-results", title: "9"}
- {uri: "https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-order-accepting-tariff-revisions-under-er26-455", title: "10"}